Landmark precision
Forging a legacy of innovation
Using an integrated, data-driven workflow, Landmark Construction turned a daunting challenge — preparing 1,600 acres of land to host one of the largest EV plants in the U.S. — into a masterclass in efficiency and collaboration, proving that the future of construction is truly connected.
Strength in numbers
Landmark Construction’s secret to success: meticulous coordination and precision in a connected construction environment.
EARTHMOVING
24 million cubic yards
Amount of material moved to help finish the masterplan for an EV manufacturing site in South Carolina.
500,000 tons
Amount of stone needed to be placed to secure the site’s foundation.
CONSTRUCTION
1,600 acres
Size of "Project Connect" — one of the largest electric vehicle manufacturing plants in the United States.
Up to 70,000 cubic yards
Amount of material Landmark moved daily by establishing an innovative live data connection across the entire site.
FLEET
150
Pieces of equipment on the site at any given time throughout the construction phase.
30
Number of both excavators and dozers on the worksite. The equipment pool also included two motor graders and a scraper fleet, along with six rovers, two drones and 100-plus off-road dump trucks.
Electrifying performance
Landmark's delivery sparks success
Images
Landmark in action

Slide 1 of 5