About the project
Category: Industrial Project Company: SUD ETUDES ET EQUIPEMENTS INDUSTRIE Project Location: AIRVAULT, France
The project in pictures





Trimble is a global technology company that connects the physical and digital worlds, transforming the ways work gets done. With relentless innovation in precise positioning, modeling and data analytics, Trimble enables essential industries including construction, geospatial and transportation. Whether it's helping customers build and maintain infrastructure, design and construct buildings, optimize global supply chains or map the world, Trimble is at the forefront, driving productivity and progress.
We tried to combine the products in your guest cart with your saved cart, but we encountered an issue while merging them. When choosing a subscription, please select either monthly or yearly as they cannot be combined. Kindly review your cart before proceeding to checkout.
The software you are trying to purchase is not available in your country or region.
Your currency has been changed to match the currency associated with your account address.
Your cart has been updated for two reasons. First, the prices now reflect the currency associated with your account address. Second, you've added too many of one item to your cart. Please review your cart before proceeding.
While combining the products in your guest cart with your saved cart, at least one item in your cart has exceeded the maximum allowable quantity. Please review and correct your cart before proceeding to checkout.
We were unable to access your account information. Please contact customer support for assistance.

Category: Industrial Project Company: SUD ETUDES ET EQUIPEMENTS INDUSTRIE Project Location: AIRVAULT, France









Length of longest conveyor: 175 metres Maximum height: 60 metres Tonnage: 695 tonnes Quantity of concrete: 683 m3
Tekla Structures Tekla Model Sharing
The aim of the project is to build a state-of-the-art cement plant on a European scale, increasing yields while greatly reducing the carbon footprint (by 27%).
Our study concerns three conveyors used to transport clinker in a cement plant, and a building used to support incinerated silos (reinforced concrete and steel structure).
The biggest challenge was to design conveyors with significant overhangs so as not to add loads to the existing storage silos, with strict constraints on displacements for the mechanical conveyors supported by our structures.
Design office during the execution phase