Trimble Construction Awards - Sud Etudes et Equipements Industrie, Marina Marseille JO 2024

About the project

Company: SUD ETUDES ET EQUIPEMENTS INDUSTRIE Project location: MARSEILLE 13008, France

The project in pictures

Trimble Construction Awards - Sud Etudes et Equipements Industrie, Marina Marseille JO 2024
Trimble Construction Awards - Sud Etudes et Equipements Industrie, Marina Marseille JO 2024
Trimble Construction Awards - Sud Etudes et Equipements Industrie, Marina Marseille JO 2024
Trimble Construction Awards - Sud Etudes et Equipements Industrie, Marina Marseille JO 2024
Trimble Construction Awards - Sud Etudes et Equipements Industrie, Marina Marseille JO 2024
Trimble Construction Awards - Sud Etudes et Equipements Industrie, Marina Marseille JO 2024
Trimble Construction Awards - Sud Etudes et Equipements Industrie, Marina Marseille JO 2024
Trimble Construction Awards - Sud Etudes et Equipements Industrie, Marina Marseille JO 2024
Trimble Construction Awards - Sud Etudes et Equipements Industrie, Marina Marseille JO 2024
Trimble Construction Awards - Sud Etudes et Equipements Industrie, Marina Marseille JO 2024
Trimble Construction Awards - Sud Etudes et Equipements Industrie, Marina Marseille JO 2024
Trimble Construction Awards - Sud Etudes et Equipements Industrie, Marina Marseille JO 2024
Trimble Construction Awards - Sud Etudes et Equipements Industrie, Marina Marseille JO 2024
Trimble Construction Awards - Sud Etudes et Equipements Industrie, Marina Marseille JO 2024
Trimble Construction Awards - Sud Etudes et Equipements Industrie, Marina Marseille JO 2024
Trimble Construction Awards - Sud Etudes et Equipements Industrie, Marina Marseille JO 2024
Trimble Construction Awards - Sud Etudes et Equipements Industrie, Marina Marseille JO 2024
Trimble Construction Awards - Sud Etudes et Equipements Industrie, Marina Marseille JO 2024

The project in figures

Cost of marine works: 6.9 million euros Total surface area of project: 49,000 m² North quay surface: 350 m² Inner breakwater: 750 m² Pôle France boom: 45 m² Concrete volume: 630 m3 Weight of reinforcement: 80 Tons

Trimble products used

Tekla Structures Tekla Model Sharing

Project description

Marina of the nautical stadium for the 2024 Olympics in Marseille.

Challenges to meet

  • The challenge of this project was to design a prefabricated structure on offshore piles, interfacing with the existing quay.

  • Assembly of the prefabricated parts went very smoothly on site.

  • We studied the prefabricated structures and 3D reinforcement on Tekla Structures.

Main role of SUD ETUDES ET EQUIPEMENTS INDUSTRIE

Design office during the execution phase

Related articles

Article

Randselva bridge: closing the gap on drawing‑free design

Randselva Bridge in Norway is the world’s longest bridge to be designed and constructed using only B...
Read full article
Article

Visualize and build automated warehouse systems with SketchUp

Senior Applications Engineer at TGW, an international provider of warehouse automation solutions, sh...
Read full article
Article

What are Digital Twins?

A digital twin in construction is a dynamic, living digital replica of a physical asset—such as a bu...
Read full article