About the project

Category: Industrial project Company: INEXOM Project location: CORBEIL-ESSONES (91), France Owner: Yposkesi (founded by AFM-Téléthon & BPI France) General contractor: CBI Carpenter: Bourgogne Constructions Métalliques Envelope: ISECOBA

The project in pictures

3D rendering of a building model with a smaller, separate structure.
3D rendering of a steel building frame with different colored beams and columns.
A 3D model of a building's structural framework, showing colored steel beams and floor joists.
3D rendering of a data center with four green server racks on a raised platform, surrounded by a colorful metal framework and piping.
3D model of structural steel framework for a building, with various components highlighted in different colors.
Architectural blueprint of a metal structure showing floor plan, bracing, and support beams.
Blueprint of a metal structure for a building, showing different views and detailed technical specifications.
A modern, white industrial building with the YPOSKESI logo and SK pharmteco Company branding is shown.
Construction site with a large white building under development, workers in hard hats, and heavy machinery.
A large steel building frame, painted blue, is under construction on a sunny day with a crane overhead.
Close-up of a freshly painted blue steel structure on a powder coating line.

The project in figures

R+1 building, 54m x 54m x 13.6m high Useful floor area: approx. 5,000 m² Steel structure: approx. 350 tonnes Roofing: +3,000 m² Cladding: +3,000 m² Total investment: approx. 60 million euros

Trimble products used

Tekla Structures Tekla Model Sharing Trimble Connect

Project description

Production building (and ancillary works) for an industrial platform for R&D and the clinical and commercial manufacture of advanced therapy products (ATMPs).

INEXOM designed the steel structure and envelope:

  • Calculations, general and detailed structural steel drawings (including fabrication and installation files)

  • Layout of pans and reinforcement studies for the composite floor

  • Design, layout and detailing of roofing and cladding

Challenges to meet

The main challenges of the project were :
  • Consideration of the constraints of the various lots in a highly constrained environment inside the building (e.g. minimum clear height to be respected between levels: strong constraint on assemblies)

  • Numerous floor types (with different thicknesses) on the same level

  • Work for different customers on the same project and a single digital model

  • Special cladding complex with special supports required

The benefits of using BIM and Trimble solutions :
  • Easier management of interfaces (civil engineering, process equipment, HVAC, etc.) with various parties working in parallel

  • Simplified exchanges thanks to the visualization and sharing of information throughout the project (integration of IFCs from third-party lots and export of IFCs from our own lots)

  • Smoother management of the structure/envelope interface thanks to the organization: INEXOM was in charge of the 2 studies.

Our pride and joy:

To have participated in the construction of a pharmaceutical production plant in France dedicated to new gene therapies.

INEXOM's main role

Design office during the execution phase

Related articles

Article

Randselva bridge: closing the gap on drawing‑free design

Randselva Bridge in Norway is the world’s longest bridge to be designed and constructed using only B...
Read full article
Article

What are Digital Twins?

A digital twin in construction is a dynamic, living digital replica of a physical asset—such as a bu...
Read full article
Article

Visualize and build automated warehouse systems with SketchUp

Senior Applications Engineer at TGW, an international provider of warehouse automation solutions, sh...
Read full article